Progress Meeting #1 held between GSA, ESSP and Pildo Labs

The first Progress Meeting of the SHERPA project was held last 16th July between the GSA (European GNSS Agency), the ESSP and Pildo Labs. This meeting was intended to track progress level of activities within SHERPA in Q1, and to identify possible risks and actions.

WP0000, WP1000 and WP3000 had already started their activities as planned in the accepted schedule of project. WP4000 started shortly after the meeting presenting a change in the planning due to anticipation of WP4300 activities to finish on Mid Term Review. The remaining work package (WP2000) is following current schedule and will be starting after summer time and in line with Procedure Design Workshop (to be held in Tallinn by mid September).